Kizildere Geothermal Power Plant 2 is an 80MW geothermal power project. It is located in Denizli, Turkey. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in September 2013.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Geothermal | 80 | 80 | – | Active | Denizli, Turkey | Zorlu Dogal Elektrik Uretimi |
---|
Description
The project is developed and owned by Zorlu Dogal Elektrik Uretimi.
Kizildere Geothermal Power Plant 2 runs at a temperature of 217.
The project cost is $250m.
Kizildere Geothermal Power Plant 2 (Kizildere Phase II) consists of 2 turbines with 10MW nameplate capacity.
Development Status
The project got commissioned in September 2013.
Contractors Involved
Kizildere Geothermal Power Plant 2 (Kizildere Phase I) is equipped with Fuji Electric FA Components & Systems turbine. The phase consists of 1 turbine with 60MW nameplate capacity.
About Zorlu Dogal Elektrik Uretimi
Zorlu Dogal Elektrik Uretimi AS operates as an energy company. The company generates, transmits, and distributes electricity. It serves clients in Turkey. It is headquartered in Istanbul, Turkey.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.