Korstaverket G 2 Plant is a 21MW biopower project. It is located in Medelpad, Sweden. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in December 2006.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 21 | 21 | – | Active | Medelpad, Sweden |
---|
Description
The project is currently owned by Sundsvall Energi.
The project generates 120GWh of electricity. The project cost is $86.134m.
Household waste which is a kind of municipal solid waste is used as a feedstock to power the project.
Development Status
The project got commissioned in December 2006.
Contractors Involved
Siemens was selected as the steam turbine supplier for the project. The company provided 1 turbine with 21MW nameplate capacity.
Babcock & Wilcox Volund supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.