Koru RES is a 52.8MW onshore wind power project. It is located in Canakkale, Turkey. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in May 2015.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 52.8 52.8 Active Canakkale, Turkey Eskoda Enerji Uretim Pazarlama Ithalat ve Ihracat Anonim Sirketi

Description

The project was developed by Eskoda Enerji Uretim Pazarlama Ithalat ve Ihracat Anonim Sirketi and is currently owned by Borusan EnBW Enerji Yatirimlari ve Uretim.

The electricitiy generated from the plant has offsetted 90,000t of carbon dioxide emissions (CO2) a year. The project cost is $102.59m.

Development Status

The project is currently active. The project got commissioned in May 2015.

Contractors Involved

Vestas Wind Systems was selected as the turbine supplier for the wind power project. The company provided 16 units of V112-3.3 MW – IEC IB turbines, each with 3.3MW nameplate capacity.

Vestas Wind Systems is the O&M contractor for the wind power project for a period of 5 years.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.