Lishi Datuhe Cogeneration Plant is a 700MW coal fired power project. It is located in Shanxi, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2017.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 700 700 Active Shanxi, China Jinneng Holding Power Group; Shanxi Datuhe Mining Investment

Description

The project is developed and owned by Jinneng Holding Power Group and Shanxi Datuhe Mining Investment. Shanxi Datuhe Mining Investment has 49% stake in the project.

It is a Steam Turbine with Cogen power plant.

The project generated 3,500,000MWh of electricity. The project cost is $548.92m.

Development Status

The project got commissioned in December 2017.

Contractors Involved

Shanxi Electric Power Engineering was selected to render EPC services for the coal fired power project.

Dongfang Electric was selected as the turbine supplier for the Coal fired project.

Dongfang Electric supplied steam boiler for the project.

About Jinneng Holding Power Group

Jinneng Holding Power Group Co Ltd (Jinneng Group) is a company which provides clean energy as the main industry, coal, electric power (grid), real estate as auxiliary industries, and modern service and finance as new industries. It is headquartered in Taiyuan, Shanxi, China.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.