Madinah PP2 Gas Turbine Power Plant is a 284MW oil fired power project. It is located in Al Madinah, Saudi Arabia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1977.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 284 284 Active Al Madinah, Saudi Arabia

Description

The project is currently owned by Saudi Electricity with a stake of 100%.

It is a Gas Turbine power plant.

Development Status

The project got commissioned in 1977.

Power Purchase Agreement

The power generated from the project is sold to Saudi Electricity under a power purchase agreement.

Contractors Involved

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit I) is equipped with GE Power GT9D gas turbines.

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit II) is equipped with GE Power GT9D gas turbines.

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit III) is equipped with GE Power GT9D gas turbines.

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit IV) is equipped with GE Power GT11D5 gas turbines.

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit V) is equipped with GE Power GT11D5 gas turbines.

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit VI) is equipped with GE Power MS7001EA gas turbines.

Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit VII) is equipped with GE Power MS7001EA gas turbines.

GE Power supplied WY 14L – 061 LLT electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit I).

GE Power supplied WY 14L – 061 LLT electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit II).

GE Power supplied WY 14L – 061 LLT electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit III).

GE Power supplied WY 18L-066 LLT electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit IV).

GE Power supplied WY 18L-066 LLT electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit V).

GE Power supplied 7A6 electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit VI).

GE Power supplied 7A6 electric generator for the Madinah PP2 Gas Turbine Power Plant (Madinah PP2 Gas Turbine Power Plant Unit VII).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.