Mazegawa No.2 is a 66.4MW hydro power project. It is located on Mazekawa river/basin in Gifu, Japan. The project is currently active. It has been developed in single phase. The project construction commenced in 1966 and subsequently entered into commercial operation in 1976.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 66.4 | 66.4 | – | Active | Gifu, Japan |
---|
Description
The project is currently owned by Chubu Electric Power.
Mazegawa No.2 is a reservoir based project. The hydro reservoir capacity is 9.74 million cubic meter. The net head of the project is 70.6m.
Development Status
The project construction commenced in 1966 and subsequently entered into commercial operation in 1976.
Contractors Involved
Toshiba Energy Systems and Solutions was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine with 68MW nameplate capacity.
Toshiba Energy Systems and Solutions supplied 1 electric generator for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.