Receive our newsletter – data, insights and analysis delivered to you
  1. Market Data
November 29, 2021

McDonough-Atkinson Combined Cycle Power Plant, US

By Carmen

McDonough-Atkinson Combined Cycle Power Plant is a 2,520MW gas fired power project. It is located in Georgia, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2011.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 2,520 2,520 Active Georgia, the US

Description

The project is currently owned by Georgia Power with a stake of 100%.

It is a combined cycle gas turbine (ccgt) power plant. The fuel is procured from Southern Natural Gas Company.

The project generated 15,354,566MWh of electricity.

Development Status

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

The project got commissioned in December 2011.

Contractors Involved

McDonough-Atkinson Combined Cycle Power Plant (McDonough-Atkinson Combined Cycle Power Plant Block I) is equipped with Mitsubishi Power M501G1 – 60Hz gas turbines. The phase consists of 2 gas turbines with 231.5MW nameplate capacity.

McDonough-Atkinson Combined Cycle Power Plant (McDonough-Atkinson Combined Cycle Power Plant Block I) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 375MW nameplate capacity.

McDonough-Atkinson Combined Cycle Power Plant (McDonough-Atkinson Combined Cycle Power Plant Block II) is equipped with Mitsubishi Power M501G1 – 60Hz gas turbines. The phase consists of 2 gas turbines with 231.5MW nameplate capacity.

McDonough-Atkinson Combined Cycle Power Plant (McDonough-Atkinson Combined Cycle Power Plant Block II) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 375MW nameplate capacity.

McDonough-Atkinson Combined Cycle Power Plant (McDonough-Atkinson Combined Cycle Power Plant Block III) is equipped with Mitsubishi Power M501G1 – 60Hz gas turbines. The phase consists of 2 gas turbines with 231.5MW nameplate capacity.

McDonough-Atkinson Combined Cycle Power Plant (McDonough-Atkinson Combined Cycle Power Plant Block III) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 375MW nameplate capacity.

Nooter/Eriksen supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU