Mehboobnagar – Maheshwaram Line is a 400kV overhead line with a length of 98km from Mehboobnagar, Telangana, India, to Maheshwaram, Telangana, India.

Construction works on the Mehboobnagar – Maheshwaram Line started in 2016 and the project was commissioned in 2017.

Description

The Mehboobnagar – Maheshwaram Line, which is an overhead line, is being operated by Sterlite Grid. The Mehboobnagar – Maheshwaram Line is a new line. The line carries alternating current (AC) through double circuit cable.

Mehboobnagar – Maheshwaram Line project development status

The development of the Mehboobnagar – Maheshwaram Line project was approved by Telangana State Electricity Regulatory Commission in 2016 and the project works were completed in 2017.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.