Mejia Thermal Power Station is a 2,340MW coal fired power project. It is located in West Bengal, India. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1997.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 2,340 2,340 Active West Bengal, India

Description

The project is currently owned by Damodar Valley.

It is a steam turbine power plant. The fuel is procured from Barjora (North) mine.

Development Status

The project got commissioned in December 1997.

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

Power Purchase Agreement

Dakshin Haryana Bijli Vitran Nigam and Uttar Haryana Bijli Vitran Nigam are the power offtakers from the project.

Contractors Involved

Bharat Heavy Electricals was selected to render EPC services for the Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit I) project. Bharat Heavy Electricals was selected to render EPC services for the Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit II) project. Bharat Heavy Electricals was selected to render EPC services for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit V) project. Bharat Heavy Electricals was selected to render EPC services for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit VI) project.

Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Unit III) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Unit IV) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Unit V) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Mejia Thermal Power Station (Mejia Thermal Power Station Unit VI) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit I).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit II).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit I).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit II).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit III).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit IV).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit V).

Bharat Heavy Electricals supplied electric generator for the Mejia Thermal Power Station (Mejia Thermal Power Station Unit VI).

Bharat Heavy Electricals supplied steam boiler for the Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit I).

Bharat Heavy Electricals supplied steam boiler for the Mejia Thermal Power Station (Mejia Thermal Power Station Phase II Unit II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU