MGHE Jogfalls is a 139.2MW hydro power project. It is located on Sharavathy river/basin in Karnataka, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1952.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 139.2 139.2 Active Karnataka, India

Description

The project is currently owned by Karnataka Power.

The net head of the project is 356m. The project generated 200 GWh of electricity.

Development Status

The project got commissioned in 1952.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Contractors Involved

Boving was selected as the turbine supplier for the hydro power project. The company provided 4 units of pelton turbines, each with 13.2MW nameplate capacity.

Boving was selected as the turbine supplier for the hydro power project. The company provided 4 units of pelton turbines, each with 21.6MW nameplate capacity.

The electric generators for the project were procured from Andritz Hydro and GE Renewable Energy.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.