Miksova is a 93.6MW hydro power project. It is located on Vah river/basin in Slovakia. The project is currently active. It has been developed in single phase. The project construction commenced in 1958 and subsequently entered into commercial operation in 1963.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 93.6 | 93.6 | – | Active | Slovakia |
---|
Description
The project is currently owned by Slovenske elektrarne.
The hydro reservoir capacity is 0.15 million cubic meter. The project generated 186.5 GWh of electricity.
The nameplate capacity of electric generator(s) installed at the site is 39 MVA.
Development Status
The project construction commenced in 1958 and subsequently entered into commercial operation in 1963.
Contractors Involved
CKD Blansko Holding was selected as the turbine supplier for the hydro power project. The company provided 3 units of kaplan turbines, each with 31.2MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.