Munchen Sud Combined Cycle Power Plant is a 305MW gas fired power project. It is located in Bavaria, Germany. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1980.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 305 305 Active Bavaria, Germany

Description

The project is currently owned by Stadtwerke Munchen with a stake of 100%.

It is a CCGT with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Oil.

Development Status

The project got commissioned in 1980.

Contractors Involved

MAB Anlagenbau Germany, Siemens and VA Tech Wabag were selected to render EPC services for the gas fired power project.

The Gas fired project have been supplied by GE Power and Siemens.

Siemens supplied electric generator for the project.

Siemens supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.