Muratli is an 115MW hydro power project. It is located on Coruh river/basin in Artvin, Turkey. The project is currently active. It has been developed in single phase. The project construction commenced in 1999 and subsequently entered into commercial operation in 2005.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 115 115 Active Artvin, Turkey Yuksel Insaat

Description

The project was developed by Yuksel Insaat and is currently owned by Devlet su Isleri Genel Mudurlugu.

Muratli is a run-of-river project. The hydro reservoir capacity is 74.8 million cubic meter. The project generated 445 GWh of electricity.

The project has 2 electric generators installed at the site. The generator capacity is 64 MVA.

Development Status

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

The project construction commenced in 1999 and subsequently entered into commercial operation in 2005.

Contractors Involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 57.5MW nameplate capacity.

About Yuksel Insaat

Yuksel Insaat AS (Yuksel Insaat), a subsidiary of Yuksel Holding AS, is a construction contracting service provider. The company offers project development and project management services. It constructs and develops dams and hydro-electricity power plants, commercial and industrial infrastructure, highways and motorways, connection roads, commercial centers and shopping malls, hospitals, hotels and holiday villages, residential buildings, and marine structure projects. Yuksel Insaat also drainage line, builds tunnels and pump stations, drinking and wastewater treatment plants, water depots and irrigation systems and underground transport systems, among others. It constructs projects in Turkey, Kazakhstan, Saudi Arabia, Uzbekistan, Ukraine, Romania, Afghanistan, Iraq, the UAE, Qatar, Jordan, and Libya. Yuksel Insaat is headquartered in Ankara, Turkey.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU