Nanao Ohta Thermal Power Station is a 1,200MW coal fired power project. It is located in Ishikawa, Japan. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 1995.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,200 | 1,200 | – | Active | Ishikawa, Japan |
---|
Description
The project is currently owned by Hokuriku Electric Power with a stake of 100%.
It is a steam turbine power plant.
Development Status
The project got commissioned in March 1995.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
Nanao Ohta Thermal Power Station (Nanao Ohta Thermal Power Station Unit I) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.
Nanao Ohta Thermal Power Station (Nanao Ohta Thermal Power Station Unit II) is equipped with Toshiba Energy Systems and Solutions Tandem Compound, Four Flow, Reheat Type steam turbine. The phase consists of 1 steam turbine with 700MW nameplate capacity.
Mitsubishi Power supplied electric generator for the Nanao Ohta Thermal Power Station (Nanao Ohta Thermal Power Station Unit I).
Toshiba Energy Systems and Solutions supplied electric generator for the Nanao Ohta Thermal Power Station (Nanao Ohta Thermal Power Station Unit II).
Mitsubishi Power supplied steam boiler for the Nanao Ohta Thermal Power Station (Nanao Ohta Thermal Power Station Unit I).
IHI supplied steam boiler for the Nanao Ohta Thermal Power Station (Nanao Ohta Thermal Power Station Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.