Nardini Apore Biomass Power Plant is a 75MW biopower project. It is planned in Goias, Brazil. The project is currently in permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 2021.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 75 | – | 75 | Permitting | Goias, Brazil | Nardini Agroindustrial |
---|
Description
The project is being developed and currently owned by Nardini Agroindustrial. The company has a stake of 100%.
The project cost is expected to be around $325.148m.
Bagasse which is a kind of agricultural by-product will be used as a feedstock to power the project.
Development Status
Post completion of the construction, the project is expected to get commissioned in 2021.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.