Negishi Refinery Power Station is a 431MW oil fired power project. It is located in Kanagawa, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2003. Buy the profile here.
Description
The project is currently owned by ENEOS with a stake of 100%.
It is a Integrated Gasification Combined Cycle (IGCC) power plant that is used for Middle load.
Development status
The project got commissioned in June 2003.
Power purchase agreement
The power generated from the project is sold to Tokyo Electric Power Co Holdings under a power purchase agreement with a contracted capacity is 342MW.
See Also:
Contractors involved
JGC Holdings was selected to render engineering procurement construction services for the oil fired power project.
Mitsubishi Power was selected as the turbine supplier for the Oil fired project. The company provided 1 unit of M701F gas turbine.
Mitsubishi Power was selected as the turbine supplier for the Oil fired project. The company provided 1 unit of SRT-40.5 steam turbine.
Mitsubishi Power supplied electric generator for the project.
Mitsubishi Power supplied steam boiler for the project.
For more details on Negishi Refinery Power Station, buy the profile here.
Premium Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.