Receive our newsletter – data, insights and analysis delivered to you
  1. Market Data
January 5, 2022

Newman Combined Cycle Power Plant, US

By Carmen

Newman Combined Cycle Power Plant is a 628MW gas fired power project. It is located in Texas, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 1975.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 628 628 Active Texas, the US

Description

The project is currently owned by El Paso Electric.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder Morgan, ONEOK Westex Transmission LP.

The project generated 1,862,411MWh of electricity.

Development Status

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

The project got commissioned in August 1975.

Contractors Involved

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I) is equipped with Siemens W501 gas turbines. The phase consists of 2 gas turbines with 85MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 120MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit I) is equipped with GE Power 7E.03 gas turbine. The phase consists of 1 gas turbine with 86.5MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit II) is equipped with GE Power 7E.03 gas turbine. The phase consists of 1 gas turbine with 86.5MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 165MW nameplate capacity.

GE Power supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit I).

GE Power supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit II).

Fuji Electric supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III).

Siemens Energy supplied steam boiler for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I).

Nooter/Eriksen supplied steam boiler for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU