Newman Combined Cycle Power Plant is a 628MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 1975. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Newman Combined Cycle Power Plant

Buy the Profile

Premium Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by El Paso Electric.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder Morgan, ONEOK Westex Transmission LP.

The project generated 1,862,411MWh of electricity.

Development status

The project got commissioned in August 1975.

Contractors involved

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I) is equipped with Siemens W501 gas turbines. The phase consists of 2 gas turbines with 85MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 120MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit I) is equipped with GE Power 7E.03 gas turbine. The phase consists of 1 gas turbine with 86.5MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit II) is equipped with GE Power 7E.03 gas turbine. The phase consists of 1 gas turbine with 86.5MW nameplate capacity.

Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III) is equipped with Fuji Electric steam turbine. The phase consists of 1 steam turbine with 165MW nameplate capacity.

GE Power supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit I).

GE Power supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit II).

Fuji Electric supplied electric generator for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III).

Siemens Energy supplied steam boiler for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock I).

Nooter/Eriksen supplied steam boiler for the Newman Combined Cycle Power Plant (Newman Combined Cycle Power Plant Bock II Unit III).

For more details on Newman Combined Cycle Power Plant, buy the profile here.

This content was updated on 4 January 2024

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.