Novokuznetskaya Gas Turbine Power Plant is a 298MW gas fired power project. It is located in Penza, Russia. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 2014.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 298 298 Active Penza, Russia

Description

The project is currently owned by Siberian Generating.

It is a Gas Turbine with Cogen power plant.

The project cost is $368.626m.

Development Status

The project got commissioned in November 2014.

Contractors Involved

“Sibirenergoengineering” was selected to render EPC services for the gas fired power project.

Power Machines was selected as the turbine supplier for the Gas fired project. The company provided 2 gas turbines, each with 149MW nameplate capacity.

Power Machines supplied electric generator for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.