Osceola County – Lakefield Junction Line is a 765kV overhead line with a length of 136.8km from Osceola County, Florida, US, to Lakefield Junction, Florida, US.

The project is expected to be commissioned in 2029.

Description

Osceola County – Lakefield Junction Line is an overhead line that will be operated by MidAmerican Energy. The line will carry alternating current (AC) through double circuit cable.

Approximately $230m was financed by the authorities to undertake the construction works of the project.

Osceola County – Lakefield Junction Line project development status

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The construction works on the Osceola County – Lakefield Junction Line project will be commenced in 2027 and commissioning is expected in 2029.

About MidAmerican Energy

MidAmerican Energy Co (MidAmerican Energy), a subsidiary of Berkshire Hathaway Energy, is a regulated electric and natural gas utility company that carries out the generation, transmission and distribution and selling of electricity. The company also undertakes distribution, selling and transportation of natural gas. It caters to a diverse clientele comprising of urban and rural residential customers as well as commercial and industrial customers.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.