Pairi Daiza Brugelette Solar PV Plant is a 20MW solar PV power project. It is located in Hainaut, Belgium. The project is currently active. It has been developed in single phase. The project construction commenced in 2019 and subsequently entered into commercial operation in 2020.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 20 20 Active Hainaut, Belgium Perpetum Energy

Description

The project was developed by Perpetum Energy.

Pairi Daiza Brugelette Solar PV Plant is a roof-mounted solar project.

The project generates 20,000MWh of electricity.

Development Status

The project construction commenced in 2019 and subsequently entered into commercial operation in 2020.

Contractors Involved

Perpetum Energy was selected to render EPC services for the solar PV power project.

LONGi Green Energy Technology was selected as the supplier of the PV modules for the project. The company installed 62,750 modules at the site.

Perpetum Energy is the O&M contractor for the solar PV power project, commencing from the year 2002.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.