Paka Power Station is an 808MW gas fired power project. It is located in Terengganu, Malaysia. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in September 1995.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 808 | 808 | – | Active | Terengganu, Malaysia |
---|
Description
The project is currently owned by YTL Power International with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development Status
The project got commissioned in September 1995.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataPower Purchase Agreement
Suruhanjaya Tenaga and Tenaga Nasional are the power offtakers from the project.
Contractors Involved
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 4 units of SGT5-2000E gas turbines.
Siemens supplied electric generator for the project.
AC Boilers supplied steam boiler for the project.
YTL Power Services Sdn is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.