Parli Thermal Power Station Unit VIII is a 250MW coal fired power project. It is located in Maharashtra, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2016.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 250 | 250 | – | Active | Maharashtra, India | Maharashtra State Power Generation |
---|
Description
The project is developed and owned by Maharashtra State Power Generation.
It is a Steam Turbine power plant. The fuel is procured from Machhakata and Mahanadi coal block.
The project cost is $223.1m.
Development Status
The project got commissioned in 2016.
Contractors Involved
Sunil Hitech Engineers was selected to render EPC services for the coal fired power project.
Bharat Heavy Electricals was selected as the turbine supplier for the Coal fired project.
Bharat Heavy Electricals supplied electric generator for the project.
Bharat Heavy Electricals supplied steam boiler for the project.
About Maharashtra State Power Generation
Maharashtra State Power Generation Co Ltd (Mahagenco) is a state government-owned electricity company that company generates and supplies electricity across the state of Maharashtra in India. Mahagenco owns and operates generation facilities, and uses diverse fuel sources such as thermal, gas and hydro for power generation. The company’s power generation portfolio consists of thermal power stations, hydro generation facilities, and gas-based generation facilities. It has thermal power stations in Koradi, Nasik, Bhusawal, Paras, Parli, K’kheda, and Chandrapur. The company produces the cheapest power for consumers in state. Its power projects under development include Koradi TPS, Chandrapur TPS, and Parli TPS. Mahagenco is headquartered in Mumbai, Maharashtra, India.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.