Planicie Banderita is a 479MW hydro power project. It is located on Neuquén, Rio Black river/basin in Neuquen, Argentina. The project is currently active. It has been developed in single phase. The project construction commenced in 1969 and subsequently entered into commercial operation in 1977.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 479 | 479 | – | Active | Neuquen, Argentina | Hidronor Ingenieria y Servicios |
---|
Description
The project was developed by Hidronor Ingenieria y Servicios and is currently owned by Orazul Energy Argentina with a stake of 100%.
Planicie Banderita is a reservoir based project. The gross head of the project is 69m. The project generated 1,551 GWh of electricity.
Development Status
The project construction commenced in 1969 and subsequently entered into commercial operation in 1977.
Power Purchase Agreement
The power generated from the project is sold to Cammesa under a power purchase agreement.
Contractors Involved
Boving was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 243MW nameplate capacity.
Voith Siemens Hydro Power Generation supplied electric generator(s) for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.