Les Barrancs Wind Project is a 30MW onshore wind power project. It is planned in Catalonia, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2021 and is expected to enter into commercial operation in 2023. Buy the profile here.
Description
The project is being developed and currently owned by Naturgy Renovables. The company has a stake of 100%.
The project is expected to supply enough clean energy to power 65,000 households. The project cost is expected to be around $44.28m.
Development status
The project construction is expected to commence from 2021. Subsequent to that it will enter into commercial operation by 2023.
Contractors involved
GE Renewable Energy will be the turbine supplier for the wind power project. The wind power project consists of 10 turbines.
For more details on Les Barrancs Wind Project, buy the profile here.
About Naturgy Renovables
Naturgy Renovables SL (Naturgy Renovables) generates, transmits, and distributes electricity through solar energy. Naturgy Renovables headquartered in Spain.