Quetta Solar PV Park 1 is a 50MW solar PV power project. It is planned in Balochistan, Pakistan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2023 and is expected to enter into commercial operation in 2024. Buy the profile here.
Description
The project is being developed and currently owned by Enertech Quetta Solar. The company has a stake of 100%.
Quetta Solar PV Park 1 is a ground-mounted solar project which is planned over 250 acres.
The project cost is expected to be around $50m.
Development status
The project construction is expected to commence from 2023. Subsequent to that it will enter into commercial operation by 2024.
Power purchase agreement
The power generated from the project will be sold to Central Power Purchasing Agency under a power purchase agreement for a period of 25 years. The offtake capacity is expected to be 39.44MW.
Contractors involved
Power Construction Corporation of China is expected to render engineering procurement construction services for the solar PV power project.
Canadian Solar will be the supplier of the PV modules for the solar power project. The company is expected to provide 147,060 modules each with 340W of nameplate capacity.
Huawei Technologies is likely to be the supplier of 464 of its Sun2000 90KTL inverters to the project site.