The Tanjung Jati A Coal Fired Power plant is 1,320MW coal fired power project. It is planned in West Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the announced stage. It will be developed in multiple phases. The project construction is likely to commence in 2023 and is expected to enter into commercial operation in 2025. Buy the profile here.
Description
The project is being developed by PT Tanjung Jati Power. YTL Jawa Power Holdings and PT Bakrie & Brothers are currently owning the project having ownership stake of 80% and 20% respectively.
It is a Steam Turbine power plant.
The project cost is expected to be around $2,700m.
Development status
The project construction is expected to commence from 2023. Subsequent to that it will enter into commercial operation by 2025.
Power purchase agreement
The power generated from the project will be sold to PT PLN (Persero) under a power purchase agreement for a period of 30 years.
Contractors involved
Samsung C&T is expected to render engineering procurement construction services for the coal fired power project.
For more details on Tanjung Jati A Coal Fired Power plant, buy the profile here.