Qinghe Coal Fired Power Plant Phase II is a 600MW coal fired power project. It is located in Liaoning, China. The project is currently active. It has been developed in single phase.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 600 | 600 | – | Active | Liaoning, China |
---|
Description
The project is currently owned by Liaoning Qinghe Electric Power Generating with a stake of 100%.
It is a Steam Turbine power plant.
Contractors Involved
State Power Investment was selected to render EPC services for the coal fired power project.
Harbin Turbine was selected as the turbine supplier for the Coal fired project. The company provided 1 unit of CLN-24.2/566/566 steam turbine with 600MW nameplate capacity.
Harbin Electric Machinery supplied QFSN 600-2YHG electric generator for the project.
Harbin Boiler supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.