Salignac is an 88MW hydro power project. It is located on Durance river/basin in Provence-Alpes-Cote dAzur, France. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1976.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 88 | 88 | – | Active | Provence-Alpes-Cote dAzur, France |
---|
Description
The project is currently owned by Electricite de France with a stake of 100%.
Salignac is a reservoir based project. The hydro reservoir capacity is 6.2 million cubic meter. The gross head of the project is 28m. The project generated 250 GWh of electricity.
Development Status
The project got commissioned in 1976.
Contractors Involved
GE Renewable Energy was selected as the turbine supplier for the hydro power project. The company provided 2 units of kaplan turbines, each with 44MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.