Sirius/Aurora Solar PV Park is an 86MW solar PV power project. It is located in Northern Cape, South Africa. The project is currently active. It has been developed in single phase. The project construction commenced in 2018 and subsequently entered into commercial operation in February 2020.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 86 86 Active Northern Cape, South Africa Aurora Power Solutions; Sirius Solar PV Project One

Description

The project was developed by Aurora Power Solutions and Sirius Solar PV Project One. Scatec, H1 Holdings and KLP Norfund Investments are currently owning the project having ownership stake of 42%, 35% and 18% respectively.

Sirius/Aurora Solar PV Park is a ground-mounted solar project which is spread over an area of 250 hectares.

The project generates 217GWh electricity and supplies enough clean energy to power 40,000 households, offsetting 180,000t of carbon dioxide emissions (CO2) a year. The project cost is $140.753m.

Development Status

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The project construction commenced in 2018 and subsequently entered into commercial operation in February 2020.

Power Purchase Agreement

The power generated from the project is sold to Eskom Holdings SOC under a power purchase agreement for a period of 20 years.

Contractors Involved

Scatec was selected to render EPC services for the solar PV power project.

BYD was selected as the supplier of the PV modules for the project. The company provided 277,500 modules each with 310W of nameplate capacity.

SMA Solar Technology supplied 37 of its Sunny Central 2200 inverters to the project site.

Scatec is the O&M contractor for the solar PV power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.