St Pantaleon is a 52MW hydro power project. It is located on Enns river/basin in Lower Austria, Austria. The project is currently active. It has been developed in single phase. The project construction commenced in 1960 and subsequently entered into commercial operation in 1965.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 52 | 52 | – | Active | Lower Austria, Austria | Ennskraftwerke |
---|
Description
The project was developed by Ennskraftwerke. The project is co-owned by Energie AG Oberosterreich Trading and VERBUND Hydro Power, with their respective ownership stake of 50% each.
St Pantaleon is a run-of-river project. The project generated 261.6 GWh of electricity.
Development Status
The project construction commenced in 1960 and subsequently entered into commercial operation in 1965.
Contractors Involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 1 unit of kaplan turbine with 27.29MW nameplate capacity.
The electric generators for the project were procured from ELIN Motoren and Siemens.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.