Svorkmo is a 54.5MW hydro power project. It is located on Salmon river/basin in Trondelag, Norway. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1983.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 54.5 | 54.5 | – | Active | Trondelag, Norway |
---|
Description
Statkraft, TronderEnergi and Eidsiva Energi are currently owning the project having ownership stake of 48.6%, 35% and 12% respectively.
Svorkmo is a run-of-river project. The gross head of the project is 99m. The project generated 270 GWh of electricity.
The project has 1 electric generator installed at the site. The generator capacity is 22 MVA.
The project has 1 electric generator installed at the site. The generator capacity is 39 MVA.
Development Status
The project got commissioned in 1983.
Contractors Involved
Kvaerner Power Equipment was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.