Taber is an 81.4MW onshore wind power project. It is located in Alberta, Canada. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in September 2007.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 81.4 81.4 Active Alberta, Canada Enmax Green Power

Description

The project was developed by Enmax Green Power and is currently owned by Enmax with a stake of 100%.

The project supplies enough clean energy to power 32,000 households. The project cost is $141.14m.

Development Status

The project is currently active. The project got commissioned in September 2007.

Power Purchase Agreement

The power generated from the project is sold to Enmax under a power purchase agreement for a period of 20 years.

Contractors Involved

Hatch was selected to render EPC services for the wind power project.

Enercon was selected as the turbine supplier for the wind power project. The company provided 37 units of E-70 turbines, each with 2.2MW nameplate capacity.

About Enmax Green Power

Enmax Green Power, Inc. is a power generation and distribution company.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.