Taean IGCC Pilot Power Plant is a 346.33MW coal fired power project. It is located in South Chungcheong, South Korea. The project is currently active. It has been developed in single phase. The project construction commenced in 2011 and subsequently entered into commercial operation in August 2016.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 346.33 | 346.33 | – | Active | South Chungcheong, South Korea |
---|
Description
The project is currently owned by Korea Western Power.
It is a Integrated Gasification Combined Cycle (IGCC) power plant.
The project cost is $1,074.45m.
Development Status
The project construction commenced in 2011 and subsequently entered into commercial operation in August 2016.
Contractors Involved
Doosan Heavy Industries & Construction was selected to render EPC services for the coal fired power project.
GE Power was selected as the turbine supplier for the Coal fired project. The company supplied 7FB model gas turbines for the project.
GE Power was selected as the turbine supplier for the Coal fired project. The company supplied D11 model steam turbines for the project.
GE Power supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.