Takhiatash Combined Cycle Power Plant, Uzbekistan

By Carmen

Takhiatash Combined Cycle Power Plant is a 560MW gas fired power project. It is located in Karakalpakstan, Uzbekistan. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2020.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 560 560 Active Karakalpakstan, Uzbekistan JSC Uzbekenergo

Description

The project is developed and owned by JSC Uzbekenergo.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project generated 3,600,000MWh of electricity. The project cost is $678.2m.

Development Status

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

The project got commissioned in December 2020.

Contractors Involved

Hyundai Engineering was selected to render EPC services for the Takhiatash Combined Cycle Power Plant (Takhiatash Combined Cycle Power Plant Phase I Unit I) project. Hyundai Engineering was selected to render EPC services for the Takhiatash Combined Cycle Power Plant (Takhiatash Combined Cycle Power Plant Phase I Unit II) project. Hyundai Engineering & Construction was selected to render EPC services for the Takhiatash Combined Cycle Power Plant (Takhiatash Combined Cycle Power Plant Phase I Unit I) project. Hyundai Engineering & Construction was selected to render EPC services for the Takhiatash Combined Cycle Power Plant (Takhiatash Combined Cycle Power Plant Phase I Unit II) project.

GE Power was selected as the turbine supplier for thermal power project. The project consists of 4 turbines.

GE Power supplied electric generator for the Takhiatash Combined Cycle Power Plant (Takhiatash Combined Cycle Power Plant Phase I Unit I).

GE Power supplied electric generator for the Takhiatash Combined Cycle Power Plant (Takhiatash Combined Cycle Power Plant Phase I Unit II).

About JSC Uzbekenergo

JSC Uzbekenergo (Uzbekenergo), is a state-owned power generation company. It generates, transmits and distributes electric power to its customers in Uzbekistan. The company operates thermal power plants, hydro power plants, and heat power plants. Uzbekenergo produces and sells thermal energy to domestic and industrial consumers in various cities across the country. It also operates in coal sector. The company operates power plants in Fergana, Kashkadarya, Syrdarya, Tashkent and Navoiy regions and the Republic of Karakalpakstan. Uzbekenergo is headquartered in Tashkent, Uzbekistan.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU