Torino Nord Combined Cycle Power Plant is a 395MW gas fired power project. It is located in Piedmont, Italy. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 2011.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 395 | 395 | – | Active | Piedmont, Italy |
---|
Description
The project is currently owned by Iren Energia.
It is a CCGT with Cogen power plant.
The project cost is $310.252m.
Development Status
The project got commissioned in November 2011.
Contractors Involved
FATA EPC was selected to render EPC services for the gas fired power project.
The Gas fired project have been supplied by Ansaldo Energia and Franco Tosi Meccanica.
The electric generators for the project were procured from Ansaldo Energia and Franco Tosi Meccanica.
STF supplied steam boiler for the project.
Ansaldo Energia is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.