Ventanilla Combined Cycle Power Plant is a 524MW gas fired power project. It is located in Callao, Peru. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1997.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 524 524 Active Callao, Peru

Description

The project is currently owned by Enel Generacion Peru SAA with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel. The fuel is procured from Camisea Gas Project.

The project generated 2,386,868.38MWh of electricity. The project cost is $135m.

Development Status

The project got commissioned in 1997.

Power Purchase Agreement

The power generated from the project is sold to Sistema Electrico Interconectado Nacional under a power purchase agreement.

Contractors Involved

Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit I) is equipped with Siemens SGT6-4000F gas turbine. The phase consists of 1 gas turbine with 170MW nameplate capacity.

Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit II) is equipped with Siemens SGT6-4000F gas turbine. The phase consists of 1 gas turbine with 170MW nameplate capacity.

Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit III) is equipped with Siemens SST6-5000 steam turbine. The phase consists of 1 steam turbine with 184MW nameplate capacity.

Siemens supplied electric generator for the Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit I).

Siemens supplied electric generator for the Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit II).

Siemens supplied electric generator for the Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit III).

Vogt Power International supplied steam boiler for the Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit I).

Vogt Power International supplied steam boiler for the Ventanilla Combined Cycle Power Plant (Ventanilla CCGT Power Plant Unit II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology