Windpark Trautmannsdorf Nord is a 30.5MW onshore wind power project. It is located in Lower Austria, Austria. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2015.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 30.5 | 30.5 | – | Active | Lower Austria, Austria | Energie AG Oberosterreich; ImWind Group; Puspok Group |
---|
Description
The project was developed by Energie AG Oberosterreich, ImWind Group and Puspok Group. Energie AG Oberosterreich and Puspok Group are currently owning the project.
The project has 135m high towers.
Development Status
The project is currently active. The project got commissioned in July 2015.
Contractors Involved
Enercon was selected as the turbine supplier for the wind power project. The project consists of 10 units of E-101 / 3,050 kW turbines, each with 3.05MW nameplate capacity.
Energie AG Oberosterreich Trading is the O&M contractor for the Windpark Trautmannsdorf Nord (Trautmannsdorf Nord A), commencing from the year 2015.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.