Woodleaf is a 59MW hydro power project. It is located on Feather river/basin in California, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1963.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 59 | 59 | – | Active | California, the US |
---|
Description
The project is currently owned by South Feather Water and Power Agency.
The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 1 in number. The penstock length is 1,072.591m.
Development Status
The project got commissioned in 1963.
Contractors Involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 1 unit of pelton turbine with 60MW nameplate capacity.
Westinghouse Electric supplied 1 electric generator for the project. The generator capacity is 65.5 MVA.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.