Yili Thermal Power Plant is a 660MW coal fired power project. It is located in Xinjiang Uyghur Autonomous Region, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in January 2013.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 660 660 Active Xinjiang Uyghur Autonomous Region, China

Description

The project is currently owned by SIDC Yili Energy Development with a stake of 100%.

It is a Steam Turbine with Cogen power plant.

Development Status

The project got commissioned in January 2013.

Content from our partners
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration
Reimagining the carbon problem

Contractors Involved

PowerChina Nuclear Engineering was selected to render EPC services for the coal fired power project.

Yili Thermal Power Plant (Yili Thermal Power Plant Unit I) is equipped with Shanghai Turbine steam turbine. The phase consists of 1 steam turbine with 330MW nameplate capacity.

Yili Thermal Power Plant (Yili Thermal Power Plant Unit II) is equipped with Shanghai Turbine steam turbine. The phase consists of 1 steam turbine with 330MW nameplate capacity.

Shanghai Electric Group supplied electric generator for the Yili Thermal Power Plant (Yili Thermal Power Plant Unit I).

Shanghai Electric Group supplied electric generator for the Yili Thermal Power Plant (Yili Thermal Power Plant Unit II).

Dongfang Boiler Group supplied steam boiler for the Yili Thermal Power Plant (Yili Thermal Power Plant Unit I).

Dongfang Boiler Group supplied steam boiler for the Yili Thermal Power Plant (Yili Thermal Power Plant Unit II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU