Yuanbaoshan Power Plant is a 2,100MW coal fired power project. It is located in Inner Mongolia, China. The project is currently active. It has been developed in multiple phases.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 2,100 2,100 Active Inner Mongolia, China

Description

The project is currently owned by Yuanbaoshan Power Generation.

It is a steam turbine power plant.

Contractors Involved

Yuanbaoshan Power Plant (Yuanbaoshan Power Plant Unit I) is equipped with Harbin Turbine steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.

Yuanbaoshan Power Plant (Yuanbaoshan Power Plant Unit II) is equipped with Harbin Turbine steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.

Yuanbaoshan Power Plant (Yuanbaoshan Power Plant Unit III) is equipped with Harbin Turbine steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.

The electric generators for the project were procured from GE Power and Harbin Electric Machinery.

Harbin Boiler supplied steam boiler for the Yuanbaoshan Power Plant (Yuanbaoshan Power Plant Unit III).

Harbin Boiler supplied steam boiler for the Yuanbaoshan Power Plant (Yuanbaoshan Power Plant Unit IV).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.