Zurbaran Solar PV Park is a 42.962MW solar PV power project. It is located in Extremadura, Spain. The project is currently active. It has been developed in single phase. The project construction commenced in 2018 and subsequently entered into commercial operation in September 2019.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Solar PV | 42.962 | 42.962 | – | Active | Extremadura, Spain | Enel Green Power Espana SLU; Ingenostrum |
---|
Description
The project was developed by Enel Green Power Espana SLU and Ingenostrum. The project is currently owned by Enel Green Power Espana SLU with a stake of 100%.
Zurbaran Solar PV Park is a ground-mounted solar project which is spread over an area of 103.89 hectares.
The project cost is $45.743m.
Development Status
The project construction commenced in 2018 and subsequently entered into commercial operation in September 2019.
Contractors Involved
Jinko Solar was selected as the supplier of the PV modules for the project. The company provided 126,360 modules each with 340W of nameplate capacity.
FIMER supplied 23 of its R15015TL inverters to the project site.
About Ingenostrum
Ingenostrum SL (Ingenostrum) is a construction company that develops civil and energy infrastructural projects. The company’s services include engineering, technical and economic feasibility, planning, obtaining permits, detail engineering, operation and maintenance of facilities, consulting and auditing, and environmental assesments. It also offers bidding and construction engineering, consulting and implementation, project management, evaluation of technical solutions, contract tracking, optimization and time management, quality control supplies, construction supervision, commissioning, and monitoring and claiming guarantees, among others. The company develops power generation, transformation, transmission, and distribution projects. It has operations in Spain, Chile, and Colombia. Ingenostrum is headquartered in Sevilla, Spain.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.