View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
18 December 2020

Arkona Offshore Wind Farm, Baltic Sea

Arkona offshore wind farm, also known as Arkona Becken Südost, is a 385MW offshore facility built by E.ON in partnership with Norwegian energy company Equinor (formerly Statoil).
Arkona offshore wind farm is also known as Arkona Becken Südost. Credit: Ein Dahmer.
The wind farm features a total of 60 Siemens SWT-6.0-154 direct-drive wind turbines. Credit: Equinor ASA.
The construction of the Arkona wind farm began in August 2016. Credit: E.ON.
The Arkona wind farm was connected to the grid node in Lubmin. Credit: Equinor ASA.

Arkona offshore wind farm, also known as Arkona Becken Südost, is a 385MW offshore facility built by E.ON in partnership with Norwegian energy company Equinor (formerly Statoil). It is located 35km north-east of Rügen Island in the Baltic Sea.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

Statoil purchased a 50% stake in the project from E.ON and the two partners announced their final investment decision on the wind farm in April 2016. The construction of the wind farm began in August 2016, and the facility was commissioned in April 2019.

The $1.4bn project was designed to supply renewable power for approximately 400,000 homes and offset 1.2 million tonnes (Mt) of carbon dioxide emissions a year.

It created up to 400 construction jobs and 50 direct permanent jobs in addition to 100 indirect jobs.

Arkona offshore wind farm make-up

The wind farm has a total of 60 Siemens SWT-6.0-154 direct-drive wind turbines rated at approximately 6MW each. The turbines have a rotor diameter of 154m and 75m-long rotor blades, which enable them to provide an 18,600m² swept area.

The three-bladed turbines have a speed range between 5rpm and 11rpm. They rest on monopile foundations that were installed at depths, ranging between 23m and 37m.

The turbines are spread over an area of approximately 40km² and are interconnected by offshore cables.

Arkona Becken Südost wind farm construction

Major components of the offshore wind farm were pre-assembled on the wharf of the Port of Sassnitz in Mecklenburg-Vorpommern, which served as a logistics base for the project, during the construction phase.

“The wind farm has a total of 60 Siemens SWT-6.0-154 direct-drive wind turbines rated at approximately 6MW each.”

The components from the wharf were loaded onto ships for installation in the water. The port developed the necessary wharf space and berths for the rapid loading and unloading of the project components.

As of September 2018, 44 wind turbines were installed and the first electricity was supplied to the German grid during the same month.

The construction of the wind farm was completed in October 2018 and all turbines were installed in less than three months. The turbines reached peak production in 2019.

Grid connection

The wind farm is installed with a 5,000t electric offshore transformer station, which will deliver the electricity generated by the wind turbines to the land via sea cables.

The substation is operated by the wind farm operating station in the Port of Mukran, Sassnitz, while the monitoring and controlling of the operations are performed by E.ON’s Offshore Marine Coordination Center in Hamburg.

The Arkona wind farm was connected to the grid node in Lubmin through the Ostwind 1-2 (System 261) and Ostwind-1-3(System 265 &281) offshore cable construction project developed by 50Hertz.

Contractors involved

The electricity produced by the wind farm is purchased traded by Engie under a four-year power purchase agreement.

Siemens was awarded the contract to supply, install, and commission the turbines for the Arkona offshore wind farm, which represented the first order for the company’s large direct-drive turbines for a Baltic Sea wind farm.

The contract for Siemens further includes turbine servicing and maintenance for two years in collaboration with a team from E.ON. The Siemens team monitors the turbines from its remote diagnostics centre in Brande, Denmark.

E.ON awarded the contract for inter-array cabling to interconnect the turbines to VBMS in April 2016.

A2SEA was awarded the contract to install the turbines, which will be performed using its offshore installation vessel Sea Challenger.

Van Oord was contracted to supply and install the monopile foundations, including the transition pieces, using its heavy lift installation vessel named Svaven by 2017.

DHI Group provided hydrography and metocean data for the project in 2010. Strabag Offshore developed a wind measuring platform to help with deciding the layout of the turbines and foundations.

Fugro Consult performed the main geotechnical investigation for the project, under a contract awarded by E.ON in 2011, using its jack-up vessel Excalibur and geotechnical drilling vessel MV Fugro Commander. Fugro drilled 79 boreholes into the seabed to perform the necessary tests at multiple locations for the offshore turbines and the transformer substation.

Nexans provided 76km of energy cables to E.ON for the Arkona wind farm.

In June 2016, DNV GL secured the project certification contract for the new wind farm. The contract included inspection stages throughout manufacturing, transport, installation, and commissioning of the wind farm.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology