15 March 2022

Kidston Pumped Storage Hydro Project, Queensland, Australia

Kidston will be the world’s first pumped storage hydropower facility to use an abandoned mine site.
The 250MW Kidston pumped storage hydro project is being developed at the former Kidston mine site in Queensland, Australia. Credit: Genex Power.
Completion of the pumped storage hydro project is expected in 2024. Credit: Genex Power.
The project will involve two reservoirs. Credit: Genex Power.

The Kidston pumped storage hydro project (K2-Hydro) is a 250MW pumped storage power plant under construction in Queensland, Australia. It is Australia’s first pumped hydro storage project in more than 40 years and will be the country’s third-biggest electricity storage facility following its commissioning.

The project is being developed by Genex Power (Genex), a renewable energy generation and storage company based in Australia.

Construction of the K2-Hydro project commenced in January 2022, and completion is expected in the fourth quarter (Q4) of 2024.

The project forms an important part of Genex Power’s Kidston Clean Energy Hub, which is an integrated solar, wind and hydroelectricity generation and storage hub being developed in stages.

Upon completion, the Kidston pumped storage facility will store and dispatch 1,870MWh of electricity each generation cycle.

Kidston pumped storage hydro project location

The K2-Hydro project is being developed on the site of the historical Kidston gold mine in northern Queensland, Australia. The mine, which operated for more than 90 years, was closed in 2001.

The site is located 270km north-west of Townsville city. Two large adjacent pits at the abandoned mine site will be converted into the upper and lower reservoirs for pumped storage hydropower generation.

K2-Hydro project background

The former Kidston gold mine in northern Queensland was constructed and operated by Placer Dome, a global mining company acquired by Barrick Gold in 2006.

Genex acquired the mine from Barrick Gold in June 2014 as part of its plans to develop a clean energy hub, including a pumped storage hydropower station at the historical mine site.

A technical feasibility study for the K2-Hydro project was completed in November 2016, followed by an optimised technical feasibility study completed in October 2017.

Project financing

Financial closure for the project was achieved in May 2021. The project is funded by a 15-year debt facility worth A$610m ($469.29m) from Northern Australia Infrastructure Facility (NAIF), a non-recoupable grant worth A$47m ($36.15m) from the Australian Renewable Energy Agency (ARENA), and an equity contribution of A$118.5m ($86.23m) from Genex.

Electric Power Development (J-POWER), a Japanese public utility company, invested A$25m ($19.39m) in Genex and acquired a 10% stake in the company in May 2021. The investment was used as part of Genex’s equity contribution to the project.

In December 2015, Genex secured a loan worth A$4m ($2.91m) from the federal government agency ARENA to complete a detailed feasibility study for the project. ARENA also provided a A$5m ($3.63m) loan to support pre-financial close activities.

Kidston pumped storage reservoir details

The pumped storage hydro project will utilise the Wises pit, a shallow but broad water body, as the upper reservoir. The Eldridge pit, which is 320m deep, was chosen as the lower reservoir as it currently holds most of the 27 gigalitres (GL) of water located within the scheme.

The Wises Pit walls will be broadened and reinforced to create a large, relatively shallow dam using existing waste rock dumps at the site. The dam will feature a high-density polyethylene (HDPE) liner as a cost-effective seal.

The upper reservoir will be connected to an underground powerhouse through two concrete-lined vertical pressure tunnels with a vertical drop of 251m. Two 340m-long concrete-lined horizontal pressure tunnels will connect the powerhouse to the lower reservoir.

K2-Hydro power plant make-up

The underground powerhouse of the pumped storage project will be built inside a cavern measuring 90m long, 17.5m wide and 45m high.

It will be installed with two 125MW reversible pump Francis turbine units, two main inlet valves, two 275kV step-up transformers and two draft tube gates. The turbines will be designed to operate at a gross water head of 222.6m.

A decline portal, measuring 1.5km in length, will be used to access the underground powerhouse.

Power transmission

The K-2 Hydro project will supply electricity to Australia’s National Electricity Market (NEM) through a new 275kV transmission line.

The transmission system will require a new 275kV substation at Mount Fox on the existing 275kV transmission network between Ross and Chalumbin. A new 186km-long, 275kV single-circuit twin phosphorous transmission line will be constructed to connect the Kidston substation to the Mount Fox substation.

Power offtake agreement

EnergyAustralia will offtake electricity from the Kidston pumped storage hydropower project under an energy storage services agreement signed with Genex in March 2020. The agreement is for ten years, with options to extend it for 30 years through two more extensions of ten years each.

EnergyAustralia will receive full operational and dispatch rights over the project. According to the agreement, Genex will receive a fixed annual rental payment, which will increase over the term.

EnergyAustralia will have the option to acquire the project for a fixed cash payment upon completion of the 30-year term.

Australia-based global law firm Ashurst advised EnergyAustralia on the negotiation and execution of the offtake agreement with Genex.

Contractors involved

Power and water consulting company Entura was appointed as the owner’s engineering consultant for the project. It completed a feasibility study in 2016, which was further optimised by Mott Macdonald in October 2017.

A joint venture (JV) between McConnell Dowell, a construction firm, and John Holland, an infrastructure and engineering company, was contracted to provide engineering, procurement and construction (EPC) services for the project.

Beon Energy Solutions was awarded the design and build contract to perform the surface infrastructure works, including grid connection and substation works.

Andritz Hydro, an electromechanical systems and services supplier based in Austria, was contracted to design, manufacture, supply and commission the two reversible pump turbine units of the plant in April 2021. Andritz will also provide operation and maintenance services for the power units.

Network utility provider Powerlink was engaged for the construction of a new transmission line between the K2-Hydro project and the main grid.

Professional services company GHD was engaged in partnership with Mott MacDonald to deliver detailed design services to the McConnell Dowell-John Holland JV.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology