Karkamis Hydroelectric Power Plant, Turkey

 
key facts
Key Data
Order year
1996
Output
180MW
Plant type
Hydroelectric
Location
Euphrates valley, Northern Turkey
Estimated investiment
$175 million
Completion
2000
GAP project completion
2010

The 180MW Karkamis dam and hydroelectric plant cost $175 million and is one of the smaller dams in the South Eastern Anatolian Project (GAP). Dwarfed by the upstream Ataturk dam, it is 4.5km from the Turkish / Syrian border and 33km downstream from the now completed Birecik dam.

GAP (Güneydogu Anadolu Projesi, the project's name in Turkish) is a massive project to build 22 dams and 19 hydroelectric power stations as well as encourage other kinds of economic development in almost every industry. At present GAP has 104 hydroelectric plants which generate 10.2GW. When finished, the GAP will irrigate 1.69 million hectares of land and generate 23,000GW of hydroelectricity annually. This will be more than a fifth of Turkey's electricity generation. The overall cost of the project has been set at $32 billion.

PLANT MAKE-UP

Work on Karkamis began in 1996. It has a powerhouse, spillway and two earth filled dams. The dams were built to a height of 29m above the foundation. The length of the top of the dam is 608m and there are six Kaplan turbines with horizontal axes. The 6kV generators have a rating of 35MVA. The three transformers have a rating of 35/70MVA.

The opening ceremony took place in December 1999. Each unit was brought into production one at a time, at a rate of one a month. The total cost of the project was $175 million. The whole GAP project is expected to be completed by 2010.

PLANT CONSTRUCTION

The plant was constructed by an Austro-Turkish consortium. VA Tech Elin was responsible for the electrical equipment's delivery, installation and commissioning. Voith, another Austrian company, was responsible for the delivery, installation and commissioning of six Kaplan turbines (in July 1999, Voith and Siemens announced the merging of their hydro businesses).

Verbundplan, an Austrian firm of consulting engineers, was responsible for project co-ordination. Yuksel Insaat AS (from Turkey) was responsible for hydromechanical equipment. Temelsu International Engineering Services, also from Turkey, was responsible for detailed civil engineering. The project was supported, in part, by the Austrian government.

The construction plan was for a 48-month project, and completion was a month ahead of schedule. The construction of the powerhouse and spillway, together with erection of the turbine generators, took 32 months. The second phase involved the division of the Euphrates with coffer dams. It also involved the completion of the turbines, and the earth filling of the dams.

POLITICAL OBJECTION TO DAMS

The dams on the Euphrates have been the subject of strenuous objections from Syria and Iraq. Syria is downstream of the dams. The country formally objected in both 1995 and 1996. As a desert country, it sets a premium on water for irrigation and other purposes. The main fear on the part of these countries is that Turkey, by accident or design, will disrupt the flow of the Euphrates to Syria's disadvantage.

This is a real fear on the part of both Iraq and Syria. Both countries have a history of chequered relations with their northern neighbour. Indeed, in 1990, UN warplanes bombed Iraq from Turkish bases, and Syria is made nervous by Turkey's close relationship with Israel. Both Syria and Iraq have been accused of supporting Kurdish separatists in Turkey.

REDUCING SEPARATISM

The project was also designed to help Turkey suppress its troubles with the Kurds. Kurdish rebels have been waging war on the Turkish government since 1984, in their quest for an independent or autonomous homeland. By creating economic and social development, the GAP project was intended to reduce Kurdish separatism.

Turkey is likely to persist with its power generation project in the GAP region since it is of central importance to the country's economic and social development. The electricity generation is made even more important by the continuing difficulties of Turkey nuclear programme. Turkey had been hoping to generate 10,000MW through nuclear plants by 2020, but its plants are being delayed again. There is no prospect of nuclear generation before 2006. This makes the power of the GAP plants even more vital. An additional reason for the Turkish government's interest is the political leverage GAP gives Ankara on its downstream neighbours.



Expand Image Expand Image
The Karkamis dam and hydroelectric plant is located on the Euphrates River in Southeastern Turkey.



Expand Image Expand Image
When finished, GAP will irrigate 1.69 million hectares of land and generate 23,000GW of hydroelectricity annually.



Expand Image Expand Image
The Karkamis dam is one of the smaller dams in the South Eastern Anatolian Project (GAP - Güneydogu Anadolu Projesi).



Expand Image Expand Image
VA Tech Elin delivered, installed and commissioned the electrical equipment.



Expand Image Expand Image
Karkamis has a powerhouse, spillway and two earth filled dams. Work began in 1996


Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Special Reports
White Papers
Jobs & Careers
Industry News
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area

The website for the power industry