Nuon Magnum IGCC power Plant, Netherlands

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Plant Type
IGCC Power Plant
Location
Energy Park Eemshaven, Groningen province, Netherlands
Owner
Nuon Energy
Estimated Investment
€1.5bn
Construction started
2007
Completion
2011
Output
1,200MW

The new integrated gasification combined cycle (IGCC) power plant, Nuon Magnum, is being built by the Netherlands-based energy company, Nuon. The plant is located at Eemshaven in the Groningen province in the Netherlands. The company is investing approximately €1.5bn on the plant.

The production capacity of Nuon Magnum is about 1,200MW, which is a sufficient quantity to meet the rising electricity demand in the area. Once fully operational, the plant can supply power to two million households.

The power plant employs gasification technology. Nuon launched the construction of the plant in 2007. Delays in obtaining environmental related permits caused it to stop construction in May 2008. Nuon expects to resume construction in August 2009. The plant will start power generation in 2011.

Plant details

The power plant is located at the Energy Park Eemshaven, an industrial area dedicated to energy related businesses.

Eemshaven was chosen as the site for the power plant in July 2006, since it provides cooling water which is essential for the gasification process. Another reason for the location choice is that the Eemshaven port infrastructure facilities support the importing of fuels for the power plant.

The plant can generate power using wide range of organic materials including coal, petroleum and biomass.

Designed based on the multi-fuel concept, the plant can generate power using a wide range of organic materials including coal, petroleum and biomass. By utilising a wide range of fuels the plant can achieve large-scale production capacity. Moreover, by using biomass the electricity can be generated in a clean way.

Honeywell will automate the plant by installing an umbrella system to connect the coal gasification, power plant and auxiliary systems in the plant.

Nuon is also planning to install a carbon dioxide (CO2) capture plant at the Nuon Magnum power plant. It has already commenced the pilot programme for CO2 capture at its gasification power plant in Buggenum located in Limburg Province.

Grid network

The grid network for the IGCC power plant is provided by TenneT, the national grid operator in the Netherlands. TenneT has sanctioned the required connection for the Nuon Magnum plant to the 380kV high-voltage grid in 2007.

Nuon entered into a contract in this regard with TenneT in January 2007. The grid manager of TenneT expects to complete the 380kV station in 2009.

The Nuon Magnum plant will produce power on the Dutch electricity grid. Since the Dutch grid could not support the new electricity production of 1,200MW at the Nuon's plant, TenneT has provided the required transmission facility.

Groningen Seaports and TenneT helped Nuon in finalising a 4km route for the high-voltage connection overground, comprising two circuits. The route will connect the respective 380kV stations of TenneT and Nuon Magnum plant.

Construction

In 2007, Nuon started the construction of the Nuon Magnum power plant. However, the construction has been phased out due to the high construction costs. It was planned that the natural gas-fired part of the power plant would be built in first phase, and the coal and biomass gasification facilities would be included in second phase.

For the construction of the power plant, various licences were required under Environmental Management Act (WM), Water Management Act (WVO/WWH) and Pollution of Surface Waters Act. In May 2008, Nuon decided to stop the plant construction for one year as delays occurred in the permit procedures. Now, the company has obtained the necessary permits from the authorities. Construction of the plant is expected to restart in the end of August 2009.

Nuon has awarded a €1bn contract to the Mitsubishi Group for constructing the gas-fired part of the power plant. As the main contractor, Mitsubishi will manage the entire project and has engaged sub-contractors to execute the project. The sub-contractors include Ballast Nedam, NEM, FIP (Fabricom, Irem, Pontecelli) and ABB.

Ballast Nedam is responsible for civil works and NEM is engaged in the boilers construction. FIP is involved in the mechanical construction and ABB performs high voltage installations.

Technology

Coal gasification technology is used for electricity generation in the Nuon Magnum plant. The gasification process begins with the mixing and grinding of coal to form pulverised coal. The pulverised coal is mixed with the milled biomass, stored under nitrogen and pressurised.

Later, oxygen is added to the coal and converted into combustible gas (syngas). The gas is then cleaned and cooled. After washing with water, it is de-sulphurised to get purified syngas. Nitrogen is used to thin the syngas and low nitrogen oxide (NOx) emissions are achieved after it gets saturated with water vapour.

The coal gasification technology reduces CO2 emissions and is environmentally sound compared to conventional power plants.

The saturated syngas is combusted to drive the gas turbine. The heat released in combustion is used to create steam, which drives steam. The gas and steam turbines drives the generator in tandem and the electricity is produced in the generator. The entire process is known as Integrated Gasification Combined Cycle (IGCC). The coal gasification technology reduces CO2 emissions and is environmentally sound compared to conventional power plants.

The CO2 capture plant significantly absorbs the CO2 emissions released from the power plant. The knowledge gained in the pilot programme will be used in the Nuon Magnum power plant.

Local environmental impact

The power plant construction is believed to damage the Grey Dunes on the Ameland and Schiermonnikoog islands so the Nature Conservation Act requested that Nuon endorse measures to protect them. Nuon has arranged a breeding and resting place for birds in the zone.

Sulphur dioxide emissions and fluoride concentration from the plant had to be remedied by Nuon before it obtained permit under the WM act. Further, Protected plant and animal species are expected to face damage during to the plant construction. However, Nuon obtained dispensation from the issue, under the Flora and Fauna Act.

The company has chosen to apply damped pile-driving to minimise noise pollution to the neighbours, during the construction.



Expand Image Expand Image
Groningen Province, the Netherlands



Expand Image Expand Image
The control room at Buggenham



Expand Image Expand Image
The Nuon flag



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the power industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Special Reports
Videos
White Papers
Industry News
Gallery
Events & Exhibitions
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the power industry