Perth Wave Energy Project, Australia
Key Data
The Perth Wave Power Project is an innovative offshore development located in Western Australia. It is being developed by Carnegie Wave Energy.
The plant will have a peak rated capacity of 5MW. Carnegie signed a power offtake agreement for the project with Synergy. The electricity generated by the project will be sufficient to power approximately 3,500 households.
Carnegie claims it to be the most advanced wave power project in Australia. It will also be the first commercial demonstration project of Carnegie.
The project is expected to create up to 30 jobs. It won the Sustainable Energy Industry Excellence and Innovation Developer Award from the WA Sustainable Energy Association in March 2010.
Perth Wave project details
Carnegie Wave Energy has developed an innovative, proprietary wave energy technology called CETO. The company is developing a number of wave power projects in Australia using the CETO technology. The Perth Wave Power Project is one of them.
The project is located offshore of Fremantle at about 25m water depth in the ocean between Garden Island and Five Fathom Bank. It is situated 3km offshore from HMAS Stirling, Australia's largest naval base. It is also located close to the National Centre of Excellence in Desalination (NCED), Rockingham.
Project finances and plant make-up
The project was granted $12.5m in LEED funding by the Western Australian Government.
The offshore wave energy project is mainly made up of CETO units in water, high-pressure subsea pipelines to transfer the pressurised water onshore and a power generation system onshore.
The offshore structures are supported by pile foundations. In addition, the project involves connection of the onshore generation system to the grid network.
Development of the Western Australin power project
The Perth project was officially launched in January 2010 at Carnegie's Wave Energy Research Facility in Fremantle. It is being delivered in two stages. The first stage, with 2MW peak capacity, was launched in 2010 and completed in April 2011. The second stage will have a capacity of 3MW at peak.
Performance evaluation of the Perth commercial demonstration project will help Carnegie to develop similar commercial scale projects and start earning revenues from this innovative renewable energy technology.
Since the project is located in the area near to the HMAS Stirling Naval Base, Carnegie entered into a memorandum of understanding (MOU) with the Department of Defence in January 2009 for the development and offtake of power and water for the project.
An MOU was also signed with Hatch Engineering for the engineering, procurement, construction and management of the project.
The contract for the design of the turbine and generation system was awarded to Tyco Tamar. Two consultancies, namely RPS Consulting Engineers and Geomarine, were awarded the contract for the foundation design. The pipeline design contract was awarded to INTECSEA, a WorleyParsons Group company.
The basis of detailed design of the power system of the project was completed in December 2011.
Stage one construction
Construction of stage one of the project began in 2010 and it has been operating successfully since April 2011. The jack-up rig for drilling the pile foundation for stage one was supplied by Boskalis Australia. Stage one is initially not connected to the grid. It will operate as a stand-alone system for about 12 months for testing.
As part of stage one of the project, a commercial scale CETO unit was deployed in the Sepia Depression in 2010. The Sepia Depression is located between Garden Island and Five Fathom Bank.
The deployed system consists of the mooring and a CETO unit. A telemetry instrumentation buoy was also installed to send data back to shore for confirmation and independent verification of the unit's performance.
Stage two of the project is currently under development.
Technology included in Carnegie Wave Energy's plant
The CETO power system is anchored to the ocean floor and operates out of sight.
The technology involves tying up of an array of submerged buoys to seabed pump units.
The passing oceanic waves cause the buoys to move harmonically. The pumps are driven by the moving buoys, causing the water pressure to increase. The high-pressure water is carried to shore via a pipeline.
The pressurised water can be used to drive hydroelectric turbines to generate electricity. The entire process consumes zero electricity and causes zero emissions. The water can also be used to drive the pumps of a reverse osmosis plant for desalination, eliminating the consumption of electricity by the pumps.
The plants using CETO technology will have the least visual impact as most of the plant infrastructure and equipment is submerged.
The project will reduce greenhouse gas emissions of more than 500,000 tons over its entire life. A unique feature of the CETO technology is that it attracts marine life.