Arcos de la Frontera Combined Cycle Power Plant is a 1,626MW gas fired power project. It is located in Andalusia, Spain. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in February 2005.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,626 1,626 Active Andalusia, Spain

Description

The project is currently owned by Iberdrola Generacion Espana SAU with a stake of 100%.

It is a combined cycle gas turbine (ccgt) power plant.

Development Status

The project got commissioned in February 2005.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Contractors Involved

Iberdrola Ingenieria y Construccion SAU was selected to render EPC services for the gas fired power project.

Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block I) is equipped with GE Power 9FA gas turbine. The phase consists of 1 gas turbine.

Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block I) is equipped with GE Power D10 steam turbine. The phase consists of 1 steam turbine.

Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block II) is equipped with GE Power 9FA gas turbines. The phase consists of 2 gas turbines.

Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block II) is equipped with GE Power D10 steam turbine. The phase consists of 1 steam turbine.

Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block III) is equipped with GE Power gas turbine. The Gas fired phase consists 1 gas turbine.

Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block III) is equipped with GE Power D11 steam turbine. The phase consists of 1 steam turbine.

GE Power supplied electric generator for the Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block I).

GE Power supplied electric generator for the Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block II).

GE Power supplied electric generator for the Arcos de la Frontera Combined Cycle Power Plant (Arcos de la Frontera Combined Cycle Power Plant Block III).

Siemens Heat Transfer Technology supplied steam boiler for the project.

Iberdrola Generacion Espana SAU is the O&M contractor for thermal power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.