Gitaru is a 225MW hydro power project. It is located on Tana river/basin in Nairobi, Kenya. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1978.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 225 | 225 | – | Active | Nairobi, Kenya |
---|
Description
The project is currently owned by Kenya Electricity Generating with a stake of 100%.
The project generated 4,710 GWh of electricity.
Development Status
The project got commissioned in 1978.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 1 turbine with 81.5MW nameplate capacity.
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 72.5MW nameplate capacity.
Siemens supplied electric generator(s) for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.