Green Volt, a floating offshore wind project led by Flotation Energy and Vårgrønn, has signed an agreement with Siemens Gamesa to reserve 28 offshore wind turbines, each rated at more than 15MW.

The deal, is described as a world first for commercial-scale floating wind and secures both turbine manufacturing capacity and specialist engineering resources for the project.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The Green Volt windfarm project is located about 50 miles off the coast of Peterhead, Scotland, and is planned to have up to 560MW of generating capacity.

It has already obtained offshore consent from the Scottish Government and was awarded a 400MW Contract for Difference by the UK Government in 2024.

In a separate development, Green Volt has signed a letter of intent with the Port of Aberdeen for future anchor and mooring marshalling operations at Aberdeen South Harbour.

This arrangement is expected to support a £15m ($19.6m) investment in port infrastructure, facilities, and associated supply chain activities, though the investment is subject to final confirmation.

Green Volt project director Matt Green said: “These are landmark agreements for Green Volt and a defining moment for floating offshore wind. Reserving turbines of this scale is a world first.

“Alongside our agreement with the Port of Aberdeen, it represents significant progress towards construction, building momentum for further major contracts and investment as we move towards delivering floating wind at commercial scale.”

The Green Volt project is anticipated to drive around £2.5bn of investment, create more than 2,800 direct jobs during the construction phase, and support roughly 100 long-term operational roles.

It aims to generate renewable electricity for the UK grid and contribute to the decarbonisation of offshore oil and gas operations, supporting energy security and emissions reduction targets in the UK.

Siemens Energy UK and Ireland managing director Darren Davidson said: “Agreements such as this help build the foundation needed to accelerate deployment and support the future growth of the offshore wind sector in the UK and beyond, and we will continue to work closely with Green Volt as they progress through the remaining project delivery processes.”