The Barh Super Thermal Power Project is 3,300MW coal fired power project. It is planned in Bihar, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in November 2013. Buy the profile here.
Description
The project is being developed and currently owned by NTPC. The company has a stake of 100%.
It is a Steam Turbine power plant. The fuel will be procured from Pakri-Barwadih Mine.
Development status
Post completion of the construction, the project is expected to get commissioned in November 2013.
Contractors involved
Navayuga Engineering is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit I) project. Navayuga Engineering is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit II) project. Power Machines is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit I) project. Power Machines is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit II) project. Power Machines is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit III) project. Technopromexport is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit I) project. Technopromexport is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit II) project. Technopromexport is expected to render engineering procurement construction services for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit III) project.
Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit I) will be equipped with Leningradsky Metallichesky Zavod K-800-240 steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit II) will be equipped with Leningradsky Metallichesky Zavod K-800-240 steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit III) will be equipped with Leningradsky Metallichesky Zavod K-800-240 steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit I) will be equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit II) will be equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Electrosila is expected to be the supplier of electric generator for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit I).
Electrosila is expected to be the supplier of electric generator for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit II).
Electrosila is expected to be the supplier of electric generator for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit III).
Bharat Heavy Electricals is expected to be the supplier of electric generator for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit I).
Bharat Heavy Electricals is expected to be the supplier of electric generator for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik is likely to be the supplier of steam boiler for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik is likely to be the supplier of steam boiler for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik is likely to be the supplier of steam boiler for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage I Unit III).
Bharat Heavy Electricals is likely to be the supplier of steam boiler for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit I).
Bharat Heavy Electricals is likely to be the supplier of steam boiler for the Barh Super Thermal Power Project (Barh Super Thermal Power Project Stage II Unit II).
For more details on Barh Super Thermal Power Project, buy the profile here.
About NTPC
NTPC Ltd (NTPC) is an energy company. It has presence in the entire value chain of the power generation business. The company produces electricity and sells it to state power utilities on wholesale basis. NTPC generates electricity using coal, gas, liquid fuel, hydro and other renewable sources. It also provides consultancy, e-mobility solutions, project management and supervision; holds interests in coal mining blocks; and carries out energy trading, oil and gas exploration, training of power professionals, rural electrification, ash utilization and coal mining. NTPC is headquartered in New Delhi, India.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.